Load the cost. Load the resources. Update it twice. Then explain why the schedule index fell in a week when the finish date improved.
Ten sections. Read the brief once from start to finish, then work with the dashboard open beside P6.
A four-pad commercial foundation package. Four sectors, the same five trades on each, and one concrete crew that moves from pad to pad.
Metro Plaza is a commercial development whose building sits on four large pad foundations arranged around a central plaza. The foundation package covers the North, South, East and West pads. Each pad is cleared and graded, excavated to formation, shuttered with timber formwork, reinforced with fixed steel, then poured with ready-mix concrete and cured.
Activities within a pad run in sequence. The four concrete pours are chained so that one concrete crew, one truck and the pump move from North to South to East to West. That chain is the critical path of the job: the whole North sector, then each pour in turn.

Build the baseline programme in Primavera P6 Professional, load every activity with its resources and cost, save the baseline, then apply two weekly site reports. Report the schedule and earned value position at each data date and explain it in plain English. Every figure you should land on is published on the class dashboard, so you can check your work as you go.
The project, the client and every figure are fictional and simplified for teaching. Concrete is measured in cubic yards so that the material rates read as whole numbers.
Set these before you add a single activity. Most reconciliation problems trace back to a calendar or a default that was left alone.
| Setting | Value |
|---|---|
| Project ID and name | CFCP-2025-001, Metro Plaza Foundation Construction |
| Planned start | Tuesday 01/07/2025 |
| Calendar | CFCP-2025-001 - Standard Business Hours: Monday to Friday, 09:00 to 17:00, 8 hours a day, no holidays. Project calendar, also the default for resources |
| Duration type | Fixed Duration and Units |
| Percent complete type | Physical |
| Activity type | Task Dependent; A1200 Start Milestone; A1210 Finish Milestone |
| Relationships | All Finish to Start, zero lag, no constraints |
| Critical activities | Total float less than or equal to 0 h |
| Resource settings | Auto compute actuals off; calculate costs from units on; rate type Price / Unit |
| Currency | Pounds sterling. The XER files carry the base currency at a rate of 1, so read every figure as £ |
| Earned value | Activity % Complete (Physical) for earned value; ETC = remaining cost |
Site reports progress to close of play on Wednesday. The new data date is Thursday 09:00: Week 1 is 10/07/2025 09:00, Week 2 is 17/07/2025 09:00. Enter the date with its time shown.
Five WBS nodes, twenty activities and two milestones. The durations are given; the dates are yours to schedule.
| Code | Node | Contents |
|---|---|---|
| MS | Key Milestones | A1200 Notice to Proceed (start), A1210 Foundations Complete (finish) |
| N | North Sector | CFCP-North-100 to 140 |
| S | South Sector | CFCP-South-100 to 140 |
| E | East Sector | CFCP-East-100 to 140 |
| W | West Sector | CFCP-West-100 to 140 |
| ID | Activity | Dur (d) | Predecessors | Resources and budgeted units | Budget | ||
|---|---|---|---|---|---|---|---|
| A1200 | Notice to Proceed (NTP) | 0 | Start milestone | £0 | |||
| North | |||||||
| CFCP-North-100 | Site Preparation - North | 3 | A1200 | R001 288 h | £8,064 | ||
| CFCP-North-110 | Excavation - North Foundation | 4 | CFCP-North-100 | R002 64 h; R003 960 h; R008 32 h | £30,240 | ||
| CFCP-North-120 | Formwork Setup - North | 5 | CFCP-North-110 | R004 320 h; R012 160 m2 | £16,320 | ||
| CFCP-North-130 | Rebar Installation - North | 3 | CFCP-North-120 | R011 8.5 t; R005 432 h | £20,185 | ||
| CFCP-North-140 | Concrete Pour - North Foundation | 2 | CFCP-North-130 | R010 85 CY; R006 512 h; R007 16 h | £26,936 | ||
| South | |||||||
| CFCP-South-100 | Site Preparation - South | 2 | A1200 | R001 192 h | £5,376 | ||
| CFCP-South-110 | Excavation - South Foundation | 3 | CFCP-South-100 | R002 48 h; R003 720 h; R008 24 h | £22,680 | ||
| CFCP-South-120 | Formwork Setup - South | 4 | CFCP-South-110 | R004 256 h; R012 130 m2 | £13,132 | ||
| CFCP-South-130 | Rebar Installation - South | 2 | CFCP-South-120 | R011 6.5 t; R005 288 h | £14,165 | ||
| CFCP-South-140 | Concrete Pour - South Foundation | 2 | CFCP-North-140, CFCP-South-130 | R010 70 CY; R006 512 h; R007 16 h | £25,136 | ||
Table 4.2 continues on the next page.
| ID | Activity | Dur (d) | Predecessors | Resources and budgeted units | Budget | ||
|---|---|---|---|---|---|---|---|
| East | |||||||
| CFCP-East-100 | Site Preparation - East | 3 | A1200 | R001 288 h | £8,064 | ||
| CFCP-East-110 | Excavation - East Foundation | 4 | CFCP-East-100 | R002 64 h; R003 960 h; R008 32 h | £30,240 | ||
| CFCP-East-120 | Formwork Setup - East | 5 | CFCP-East-110 | R004 320 h; R012 110 m2 | £14,420 | ||
| CFCP-East-130 | Rebar Installation - East | 3 | CFCP-East-120 | R011 5 t; R005 432 h | £17,210 | ||
| CFCP-East-140 | Concrete Pour - East Foundation | 2 | CFCP-South-140, CFCP-East-130 | R010 55 CY; R006 512 h; R007 16 h | £23,336 | ||
| West | |||||||
| CFCP-West-100 | Site Preparation - West | 2 | A1200 | R001 192 h | £5,376 | ||
| CFCP-West-110 | Excavation - West Foundation | 3 | CFCP-West-100 | R002 48 h; R003 720 h; R008 24 h | £22,680 | ||
| CFCP-West-120 | Formwork Setup - West | 4 | CFCP-West-110 | R004 256 h; R012 175 m2 | £14,842 | ||
| CFCP-West-130 | Rebar Installation - West | 3 | CFCP-West-120 | R011 9.5 t; R005 288 h | £16,715 | ||
| CFCP-West-140 | Concrete Pour - West Foundation | 3 | CFCP-East-140, CFCP-West-130 | R010 95 CY; R006 768 h; R007 24 h | £36,504 | ||
| A1210 | Foundations Complete | 0 | CFCP-West-140 | Finish milestone | £0 | ||
| Budget at completion | £371,621 | ||||||
Budgeted cost by sector: North £101,745, South £80,489, East £93,270, West £96,117. Baseline finish Friday 01/08/2025. Float on early work: South 6 days, East 4, West 9. If any of these differ, go back before you save the baseline.
Twelve resources in three types. The type decides how P6 turns units into money.
| ID | Resource | Type | Default units/day | Limit/day | Price | Unit |
|---|---|---|---|---|---|---|
| R001 | Site Crew | Labour | 48 | 96 | £28.00/h | Hour |
| R002 | Excavator Operator | Labour | 16 | 32 | £35.00/h | Hour |
| R003 | Labourers | Labour | 80 | 240 | £25.00/h | Hour |
| R004 | Carpenters | Labour | 64 | 128 | £32.00/h | Hour |
| R005 | Rebar Workers | Labour | 48 | 144 | £30.00/h | Hour |
| R006 | Concrete Crew | Labour | 64 | 256 | £28.00/h | Hour |
| R007 | Concrete Truck | Nonlabour | 8 | 16 | £150.00/h | Hour |
| R008 | Excavator | Nonlabour | 8 | 16 | £125.00/h | Hour |
| R009 | Concrete Pump | Nonlabour | 8 | 8 | £0.00/h | Hour |
| R010 | Ready-Mix Concrete | Material | 8 | £120.00/CY | Cubic yard | |
| R011 | Reinforcement Steel | Material | 8 | £850.00/t | Tonne | |
| R012 | Formwork Ply and Props | Material | 8 | £38.00/m2 | Square metre |
The budgeted units for the three material resources. They drive the formwork, rebar and concrete pour costs.
| Sector | Ready-mix concrete (CY) | Reinforcement steel (t) | Formwork ply and props (m²) | Steel per CY |
|---|---|---|---|---|
| North | 85 | 8.5 | 160 | 0.10 t |
| South | 70 | 6.5 | 130 | 0.09 t |
| East | 55 | 5.0 | 110 | 0.09 t |
| West | 95 | 9.5 | 175 | 0.10 t |
| Total | 305 | 29.5 | 575 |
Steel divided by concrete should sit near 0.10 t per cubic yard on every pad. A pad three times higher is a typing error, not a design. Always sense-check material quantities before you load them; the planner who catches it saves the job the cost of ordering it.


Progress to close of play on Wednesday 09/07/2025. New data date Thursday 10/07/2025 09:00.
| Activity | Status and dates | Phys % | Units: actual / remaining | What site said |
|---|---|---|---|---|
| A1200 Notice to Proceed | Complete 01/07/2025 | 100% | Issued on the planned date. | |
| CFCP-North-100 Site Preparation - North | Complete Started 01/07/2025, finished 07/07/2025 | 100% | R001 480 / 0 h | Finished Monday 07/07, two days late: buried obstructions. Site crew booked 480 h against 288 h. |
| CFCP-South-100 Site Preparation - South | Complete Started 01/07/2025, finished 02/07/2025 | 100% | R001 192 / 0 h | Completed as planned. |
| CFCP-East-100 Site Preparation - East | Complete Started 01/07/2025, finished 03/07/2025 | 100% | R001 288 / 0 h | Completed as planned. |
| CFCP-West-100 Site Preparation - West | Complete Started 01/07/2025, finished 02/07/2025 | 100% | R001 192 / 0 h | Completed as planned. |
| CFCP-West-110 Excavation - West Foundation | Complete Started 03/07/2025, finished 07/07/2025 | 100% | R002 48 / 0 h R003 720 / 0 h R008 24 / 0 h | Completed as planned. |
| CFCP-South-110 Excavation - South Foundation | Complete Started 03/07/2025, finished 08/07/2025 | 100% | R002 64 / 0 h R003 720 / 0 h R008 32 / 0 h | Finished Tuesday 08/07, one day late on a soft spot. Labourers stood down for the extra day. |
| CFCP-East-110 Excavation - East Foundation | In progress Started 04/07/2025, remaining 1 d | 90% | R002 64 / 16 h R003 960 / 120 h R008 32 / 8 h | 90% dug. One more day needed, with half the labour gang. |
| CFCP-North-110 Excavation - North Foundation | In progress Started 08/07/2025, remaining 3 d | 25% | R002 32 / 48 h R003 480 / 720 h R008 16 / 24 h | Started Tuesday 08/07. Wet clay: 25% dug in two days, about half the planned output. Three more days needed at full gang. |
No formwork has started: the formwork gang mobilises on Monday 14/07. Enter nothing for any activity not listed. Then set the data date to 10/07/2025 09:00 and schedule.
Forecast finish 06/08/2025, three working days late. SPI 0.73, CPI 0.86, estimate at completion £390,677.
Progress to close of play on Wednesday 16/07/2025. New data date Thursday 17/07/2025 09:00.
| Activity | Status and dates | Phys % | Units: actual / remaining | What site said |
|---|---|---|---|---|
| CFCP-North-110 Excavation - North Foundation | Complete Started 08/07/2025, finished 11/07/2025 | 100% | R002 96 / 0 h R003 960 / 0 h R008 48 / 0 h | Finished Friday 11/07, a day earlier than last week's forecast, after a second excavator and operator were brought in. |
| CFCP-East-110 Excavation - East Foundation | Complete Started 04/07/2025, finished 11/07/2025 | 100% | R002 80 / 0 h R003 1080 / 0 h R008 40 / 0 h | Hit a rock band. Finished Friday 11/07, a day later than last week's forecast. |
| CFCP-North-120 Formwork Setup - North | In progress Started 14/07/2025, remaining 2 d | 60% | R004 192 / 128 h R012 96 / 64 m2 | Started Monday 14/07. 60% fixed. Two more days. |
| CFCP-South-120 Formwork Setup - South | In progress Started 14/07/2025, remaining 2 d | 50% | R004 192 / 128 h R012 65 / 65 m2 | Started Monday 14/07. Half done. Two more days. |
| CFCP-West-120 Formwork Setup - West | In progress Started 16/07/2025, remaining 4 d | 10% | R004 64 / 256 h R012 18 / 157 m2 | Started Wednesday 16/07 with a second gang. 10% fixed. Four more days. |
East formwork has not started: no carpentry gang free until the North or South gang moves across. Then set the data date to 17/07/2025 09:00 and schedule.
Forecast finish 05/08/2025, two working days late. SPI 0.68, CPI 0.89, estimate at completion £390,333. The finish date improved by a day and the SPI fell. Your report must explain why.
One workbook, one XER and one page of narrative. Submit through the class dashboard.
Upload D1 to D4 through the dashboard before the date your tutor gives in the cohort group. Name files with your surname first: Okafor_TT-CR-01_Answers.xlsx.
Four equally weighted parts. The narrative carries as much weight as the numbers.
| Part | What is assessed | Weight |
|---|---|---|
| Set-up and baseline | Calendar, WBS, logic, critical path, resource dictionary, budget reconciled to the pound, baseline saved and assigned | 25% |
| Progress updates | Dates, remaining duration, Physical %, actual and remaining units entered as reported; data dates correct; forecast finishes match | 25% |
| Analysis | PV, EV, AC, SPI, CPI, EAC and VAC at both data dates; the carpenter clash found and quantified | 25% |
| Narrative and presentation | Plain English explanation of the position, the SPI paradox and a recovery proposal; files named and complete | 25% |
Create labour, nonlabour and material resources; assign and reconcile budgeted cost; read a resource profile against a limit; apply weekly progress with units; read earned value and explain it to someone who does not use P6.